900.2—Applicability.

(a) DOE accepts requests for coordination of Federal authorizations under this part only for facilities that are used for the transmission of electric energy in interstate commerce for the sale of electric energy at wholesale.
(b) DOE does not accept requests for coordination under this part of Federal authorizations for electric transmission facilities located within the Electric Reliability Council of Texas interconnection.
(c) DOE does not accept requests for coordination under this part from persons that have submitted an application to the Federal Energy Regulatory Commission (FERC) for issuance of a permit for construction or modification of a transmission facility under 18 CFR 50.6 or have initiated pre-filing procedures under 18 CFR 50.5.
(d) DOE, in exercising its responsibilities under this part, will consult regularly with FERC, electric reliability organizations, and transmission organizations approved by FERC.