417.121—Safety critical preflight operations.
        
        (a) General.
         A launch operator must perform safety critical preflight operations that protect the public from the adverse effects of hazards associated with launch processing and flight of a launch vehicle. The launch operator  must identify all safety critical preflight operations in the launch schedule required by  § 417.17(b)(1). Safety critical preflight operations must include those defined in this section.
    
    
        
        (b) Countdown.
         A launch operator must implement its countdown plan, of  § 417.111(l), for each launch. A launch operator must disseminate a countdown plan to all personnel responsible for the countdown and flight of a launch vehicle, and each person must follow that plan.
    
    
        
        (c) Collision avoidance.
         A launch operator must coordinate with United States Strategic Command to obtain a collision avoidance analysis, also referred to as a conjunction on launch assessment, as required by  § 417.231. A launch operator must implement flight commit criteria as required by  § 417.113(b) to ensure that each launch meets all the criteria of  § 417.107(e).
    
    
        
        (d) Meteorological data.
         A launch operator must conduct operations and coordinate with weather organizations, as needed, to obtain accurate meteorological data to support the flight safety analysis required by subpart C of this part and to ensure compliance with the flight commit criteria required by  § 417.113.
    
    
        
        (e) Local notification.
         A launch operator must implement its local agreements and public coordination plan of  § 417.111(i).
    
    
        
        (f) Hazard area surveillance.
         A launch operator must implement its hazard area surveillance and clearance plan, of  § 417.111(j), to meet the public safety criteria of  § 417.107(b) for each launch.
    
    
        
        (g) Flight safety system preflight tests.
         A launch operator must conduct preflight tests of any flight safety system as required by section E417.41 of appendix E of this part.
    
    
        
        (h) Launch vehicle tracking data verification.
         For each launch, a launch operator must implement written procedures for verifying the accuracy of any launch vehicle tracking data provided. For a launch vehicle flown with a flight safety system, any source of tracking data must satisfy the requirements of  § 417.307(b).
    
    
        
        (i) Unguided suborbital rocket preflight operations.
         For the launch of an unguided suborbital rocket, in addition to meeting the other requirements of this section, a launch operator must perform the preflight wind weighting and other preflight safety operations required by  §§ 417.125, 417.233, and appendix C of this part.