35.620—Multifamily insured property constructed before 1960.
         Except as provided in  § 35.630, the following requirements apply to multifamily insured property constructed before 1960:
    
    
        
        (a) Risk assessment.
         Before the issuance of a firm commitment the sponsor shall conduct a risk assessment in accordance with  § 35.1320(b).
    
    
        
        (b) Interim controls.
        
        (1) 
         The sponsor shall conduct interim controls in accordance with  § 35.1330 to treat the  lead-based paint hazards identified in the risk assessment. Interim controls are considered completed when clearance is achieved in accordance with  § 35.1340.
    
    
        
        (2) 
         The sponsor shall complete interim controls before the issuance of the firm commitment or interim controls may be made a condition of the Federal Housing Administration (FHA) firm commitment, with sufficient repair or rehabilitation funds escrowed at initial endorsement of the FHA insured loan.
    
    
        
        (c) Ongoing lead-based paint maintenance activities.
         Before the issuance of the firm commitment, the sponsor shall agree to incorporate ongoing lead-based paint maintenance into regular building operations and maintenance activities in accordance with  § 35.1355(a).