250.1704—When must I submit decommissioning applications and reports?

You must submit decommissioning applications and receive approval and submit subsequent reports according to the table in this section.
Decommissioning Applications and Reports Table
Decommissioning applications and reports When to submit Instructions
(a) Initial platform removal application [not required in the Gulf of Mexico OCS Region] In the Pacific OCS Region or Alaska OCS Region, submit the application to the Regional Supervisor at least 2 years before production is projected to cease Include information required under § 250.1726 .
(b) Final removal application for a platform or other facility Before removing a platform or other facility in the Gulf of Mexico OCS Region, or not more than 2 years after the submittal of an initial platform removal application to the Pacific OCS Region and the Alaska OCS Region Include information required under § 250.1727 .
(c) Post-removal report for a platform or other facility Within 30 days after you remove a platform or other facility Include information required under § 250.1729 .
(d) Pipeline decommissioning application Before you decommission a pipeline Include information required under § 250.1751(a) or § 250.1752(a) , as applicable.
(e) Post-pipeline decommissioning report Within 30 days after you decommission a pipeline Include information required under § 250.1753 .
(f) Site clearance report for a platform or other facility Within 30 days after you complete site clearance verification activities Include information required under § 250.1743(b) .
(g) Form MMS-124, Application for Permit to Modify (APM). The submission of your APM must be accompanied by payment of the service fee listed in § 250.125 (1) Before you temporarily abandon or permanently plug a well or zone(2) Within 30 days after you plug a well * * * Include information required under §§ 250.1712 and 250.1721 .Include information required under § 250.1717 .
(3) Before you install a subsea protective device Refer to § 250.1722(a) .
(4) Within 30 days after you complete a protective device trawl test Include information required under § 250.1722(d) .
(5) Before you remove any casing stub or mud line suspension equipment and any subsea protective device Refer to § 250.1723 .
(6) Within 30 days after you complete site clearance verification activities Include information required under § 250.1743(a) .

Code of Federal Regulations

[67 FR 35406, May 17, 2002; 67 FR 44265, July 1, 2002; 67 FR 66047, Oct. 30, 2002, as amended at 71 FR 40913, July 19, 2006]