884.14—State reclamation plan approval.
        
        (a) 
         The Director shall act upon a State reclamation plan within 90 days after submittal. A State reclamation plan shall not be approved until the Director has—
    
    
        
        (1) 
         Held a public hearing on the plan within the State which submitted it, or made a finding that the State provided adequate notice and opportunity for public comment in the development of the plan;
    
    
    
        
        (3) 
         Determined that the State has the legal authority, policies, and administrative structure necessary to carry out the proposed plan;
    
    
    
    
        
        (6) 
         Determined that the proposed plan is in compliance with all applicable State and Federal laws and regulations.
    
    
        
        (b) 
         If the Director disapproves a proposed State reclamation plan, the Director shall advise the State in writing of the reasons for disapproval. The State may submit a revised proposed State reclamation plan at any time under the procedures of this section.