127.017—Alternatives.
        
        (a) 
         The COTP may allow alternative procedures, methods, or equipment standards to be used by an operator instead of any requirements in this part if—
    
    
        
        (1) 
         The operator submits a written request for the alternative at least 30 days before facility operations under the alternative would begin, unless the COTP authorizes a shorter time; and
    
    
        
        (2) 
         The alternative provides at least the same degree of safety provided by the regulations in this part.