149.610—What must the District Commander be notified of and when?
         The District Commander must be notified of the following:
    
    | When— | The District Commander must be notified— | 
|---|---|
| (a) Construction of a pipeline, platform, or single point mooring (SPM) is planned | At least 30 days before construction begins. | 
| (b) Construction of a pipeline, platform, or SPM begins | Within 24 hours, from the date construction begins, that the lights and sound signals are in use at the construction site. | 
| (c) A light or sound signal is changed during construction | Within 24 hours of the change. | 
| (d) Lights or sound signals used during construction of a platform, buoy, or SPM are replaced by permanent fixtures to meet the requirements of this part | Within 24 hours of replacement. | 
| (e) The first cargo transfer operation begins | At least 60 days before the operation. |