75.67—Retired units petitions.
        
        (b) 
         For combustion sources seeking to enter the Opt-in Program in accordance with  part 74 of this chapter that will be permanently retired and governed upon entry into the Opt-in Program by a thermal energy plan in accordance with  § 74.47 of this chapter, an exemption from the requirements of this part, including the requirement to install and certify a continuous emissions monitoring system, may be obtained from the Administrator if the designated representative submits to the Administrator a petition for such an exemption prior to the deadline in  § 75.4 by which the continuous emission or opacity monitoring systems must complete the required certification tests.