213.59—Elevation of curved track; runoff.
        
        (a) 
         If a curve is elevated, the full elevation shall be provided throughout the curve, unless physical conditions do not permit. If elevation runoff occurs in a curve, the actual minimum elevation shall be used in computing the maximum allowable operating speed for that curve under  § 213.57(b).
    
    
        
        (b) 
         Elevation runoff shall be at a uniform rate, within the limits of track surface deviation prescribed in  § 213.63, and it shall extend at least the full length of the spirals. If physical conditions do not permit a spiral long enough to accommodate the minimum length of runoff, part of the runoff may be on tangent track.