    (a)  After  a surface coal mining and reclamation permit application has been  approved but before the permit is issued, the applicant shall file a  bond with the Arkansas Department of Environmental Quality. This bond  shall be on a form furnished by the department in accordance with the  regulations issued by the Arkansas Pollution Control and Ecology  Commission. It shall be for performance or acceptable alternative  payable, as appropriate, to the department of and conditioned upon  faithful performance of all the requirements of this chapter, the  regulations issued pursuant to this chapter, and the permit.
(b)  All  forfeitures collected under this chapter shall be deposited into a  separate Mining Reclamation Trust Fund which shall be maintained by the  department. The fund may only be used to accomplish reclamation of land  covered by forfeitures of performance bonds.
(c)  The  regulations shall include provisions for posting a bond sufficient to  cover that area of land within the permit area upon which the operator  will initiate and conduct surface coal mining and reclamation operations  within the initial term of the permit and for filing additional bonds  to cover succeeding increments of area within the permit upon which the  operator intends to conduct surface coal mining and reclamation  operations.
(d)  Liability under the  bond shall be for the duration of the surface coal mining and  reclamation operation and for that period required to establish  successful revegetation in accordance with the regulations issued by the  commission.
(e)  The amount of the  bond shall be sufficient to assure the completion of the reclamation  plan if the work had to be performed by the department in the event of  forfeiture. In no case shall the bond for the entire area under one (1)  permit be less than ten thousand dollars ($10,000).
(f)  The  commission shall issue regulations setting out the criteria and  procedures for processing requests for the release of all or any part of  a performance bond provided that no bond shall be fully released until  all reclamation requirements of this chapter and the regulations issued  pursuant to this chapter are fully met. Regulations shall include  provisions for public notice of all requests for full or partial  releases, an inspection and evaluation of the reclamation work, and a  schedule for partial releases.
(g)  Any  person having an interest which is or may be adversely affected, or the  office or head of any federal, state, or local affected governmental  agency may, in accordance with      15-58-209 -- 15-58-211, file written  objections to the proposed release from bond and request an adjudicatory  public hearing.