§ 23-4-1104 - Alternative procedure for modifying rates and charges of a generation and transmission cooperative.
               	 		
23-4-1104.    Alternative procedure for modifying rates and charges of a generation and transmission cooperative.
    (a)    (1)    (A)  After  the board approves the modification in rates and charges under     23-4-1102, the generation and transmission cooperative shall file for  the approval of the Arkansas Public Service Commission an application  for the change in rates and charges and tariffs containing the proposed  change in rates and charges.
            (B)  However,  a rate rider or other rider to the generation and transmission  cooperative's base rates and charges shall not be modified under this  subchapter unless the commission determines otherwise.
      (2)  In  addition to an attachment containing the proposed tariffs to effect the  modification of the rates and charges, the application shall provide  the following:
            (A)  Proof of the board vote required by    23-4-1102;
            (B)  The proof of notice required by    23-4-1103;
            (C)  A current calculation of the generation and transmission cooperative's:
                  (i)  Times interest earned ratio;
                  (ii)  Debt service coverage ratio; and
                  (iii)  Margins as a percent of revenue for the last available calendar year;
            (D)  An  analysis of the impact of the proposed change in rates and charges on  each member cooperative's cost of wholesale power that is acquired from  the generation and transmission cooperative;
            (E)  Documentary  evidence that the impact of the proposed change in rates and charges  does not exceed five percent (5%) of the generation and transmission  cooperative's total gross revenues for the previous calendar year;
            (F)  Documentation  that shows the derivation of the generation and transmission  cooperative's proposed changes in its rates and charges; and
            (G)    (i)  Any other supporting documentation or evidence required by the commission.
                  (ii)    (a)  However, the commission shall not require the generation and transmission cooperative to prepare a cost of service study.
                        (b)  Instead  of a new cost of service study, the generation and transmission  cooperative shall rely upon the most recent commission-approved cost  allocation.
(b)  Within ninety (90)  days after the date of filing the generation and transmission  cooperative's application, the commission shall issue its final  determination regarding the proposed modification of the rates and  charges of the generation and transmission cooperative.