208.19 - RECLAMATION SCHEDULE.

        208.19  RECLAMATION SCHEDULE.
         An operator of a mine shall reclaim affected lands according to a
      schedule established by the division, but within a period not to
      exceed three years, after the filing of a report required under
      section 208.18 indicating the mining of any part of a site has been
      completed.
         For certain postmining land uses, such as a sanitary landfill, the
      division may allow an extended reclamation period.
         An operator, upon completion of any reclamation work required by
      section 208.17, shall apply to the division in writing for approval
      of the work.  The division shall within a reasonable time determined
      by divisional rule inspect the completed reclamation work.  Upon
      determination by the division that the operator has satisfactorily
      completed all required reclamation work on the land included in the
      application, the division shall release the bond or security on the
      reclaimed land, shall remove the land from registration, and shall
      terminate or amend as necessary the operator's authorization to
      conduct mining on the site.  
         Section History: Early Form
         [C71, 73, 75, 77, 79, 81, § 83A.19] 
         Section History: Recent Form
         85 Acts, ch 137, §16; 87 Acts, ch 115, § 11
         C93, § 208.19
         96 Acts, ch 1043, §12
         Referred to in § 208.17, 208.20, 208.24