§ 23-27.3-128.2.3 - Reporting.

SECTION 23-27.3-128.2.3

   § 23-27.3-128.2.3  Reporting. – The professional engineer or registered architect shall submit periodically, ina form at regular construction inspection intervals acceptable to the buildingofficial, a progress report together with pertinent comments. At the completionof construction, the engineer or architect shall submit to the buildingofficial a report as to the satisfactory completion and the readiness of theproject for occupancy (excepting any items not endangering the occupancy oroperation and listing pertinent deviations from the approved permit documents).