Section 49-41B-25.1 - Notice to commission of planned construction of certain wind energy projects.

49-41B-25.1. Notice to commission of planned construction of certain wind energy projects. Any person who plans on constructing a wind energy project consisting of wind turbines with a combined nameplate capacity that exceeds five megawatts shall notify the commission four months prior to the planned start of construction of the project. The notification shall be for informational purposes only and shall state the planned location of the project, the number of wind turbines, the nameplate capacity of the wind turbines, the planned method of interconnection, and the estimated construction start date and construction completion date. If the information provided changes, the informational filing shall be updated to reflect the changes.

Source: SL 2009, ch 246, § 1.