54-17-201 - Solicitation process required -- Exception.
               	 		 54-17-201.    Solicitation process required -- Exception.
      (1) (a)  An affected electrical utility shall comply with this chapter to acquire or constructa significant energy resource after February 25, 2005.
      (b)  Notwithstanding Subsection (1)(a), this chapter does not apply to a significant energyresource for which the affected electrical utility has issued a solicitation before February 25,2005.
      (2) (a)  Except as provided in Subsection (3), to acquire or construct a significant energyresource, an affected electrical utility shall conduct a solicitation process that is approved by thecommission.
      (b)  To obtain the approval of the commission of a solicitation process, the affectedelectrical utility shall file with the commission a request for approval that includes:
      (i)  a description of the solicitation process the affected electrical utility will use;
      (ii)  a complete proposed solicitation; and
      (iii)  any other information the commission requires by rule made in accordance withTitle 63G, Chapter 3, Utah Administrative Rulemaking Act.
      (c)  In ruling on the request for approval of a solicitation process, the commission shalldetermine whether the solicitation process:
      (i)  complies with this chapter and rules made in accordance with Title 63G, Chapter 3,Utah Administrative Rulemaking Act; and
      (ii)  is in the public interest taking into consideration:
      (A)  whether it will most likely result in the acquisition, production, and delivery ofelectricity at the lowest reasonable cost to the retail customers of an affected electrical utilitylocated in this state;
      (B)  long-term and short-term impacts;
      (C)  risk;
      (D)  reliability;
      (E)  financial impacts on the affected electrical utility; and
      (F)  other factors determined by the commission to be relevant.
      (d)  Before approving a solicitation process under this section the commission:
      (i)  may hold a public hearing; and
      (ii)  shall provide an opportunity for public comment.
      (e)  As part of its review of a solicitation process, the commission may provide theaffected electrical utility guidance on any additions or changes to its proposed solicitationprocess.
      (f)  Unless the commission determines that additional time to analyze a solicitationprocess is warranted and is in the public interest, within 60 days of the day on which the affectedelectrical utility files a request for approval of the solicitation process, the commission shall:
      (i)  approve a proposed solicitation process;
      (ii)  suggest modifications to a proposed solicitation process; or
      (iii)  reject a proposed solicitation process.
      (3)  Notwithstanding Subsection (2), an affected electrical utility may acquire or constructa significant energy resource without conducting a solicitation process if it obtains a waiver ofthe solicitation requirement in accordance with Section 54-17-501.
      (4)  In accordance with the commission's authority under Subsection 54-12-2(2), thecommission shall determine:
(a) whether this chapter or another competitive bidding procedure shall apply to apurchase of a significant energy resource by an affected electrical utility from a small powerproducer or cogenerator; and
(b) if this chapter applies as provided in Subsection (4)(a), the manner in which thischapter applies to a purchase of a significant energy resource by an affected electrical utility froma small power producer or cogenerator.
Amended by Chapter 374, 2008 General Session
Amended by Chapter 382, 2008 General Session