§ 2705. Simplified and expeditious licensing procedures

(a) Establishment of program
The Commission shall establish, in such manner as the Commission deems appropriate, consistent with the applicable provisions of law, a program to use simple and expeditious licensing procedures under the Federal Power Act [16 U.S.C. 791a et seq.] for small hydroelectric power projects in connection with existing dams.
(b) Prerequisites
Before issuing any license under the Federal Power Act [16 U.S.C. 791a et seq.] for the construction or operation of any small hydroelectric power project the Commission—
(1) shall assess the safety of existing structures in any proposed project (including possible consequences associated with failure of such structures), and
(2) shall provide an opportunity for consultation with the Council on Environmental Quality and the Environmental Protection Agency with respect to the environmental effects of such project.
Nothing in this subsection exempts any such project from any requirement applicable to any such project under the National Environmental Policy Act of 1969 [42 U.S.C. 4321 et seq.], the Fish and Wildlife Coordination Act [16 U.S.C. 661 et seq.], the Endangered Species Act [16 U.S.C. 1531 et seq.], or any other provision of Federal law.
(c) Fish and wildlife facilities
The Commission shall encourage applicants for licenses for small hydroelectric power proj­ects to make use of public funds and other assistance for the design and construction of fish and wildlife facilities which may be required in connection with any development of such proj­ect.
(d) Exemptions from licensing requirements in certain cases
The Commission may in its discretion (by rule or order) grant an exemption in whole or in part from the requirements (including the licensing requirements) of part I of the Federal Power Act [16 U.S.C. 791a et seq.] to small hydroelectric power projects having a proposed installed capacity of 5,000 kilowatts or less, on a case-by-case basis or on the basis of classes or categories of projects, subject to the same limitations (to ensure protection for fish and wildlife as well as other environmental concerns) as those which are set forth in subsections (c) and (d) of section 30 of the Federal Power Act [16 U.S.C. 823a (c) and (d)] with respect to determinations made and exemptions granted under subsection (a) of such section 30 [16 U.S.C. 823a (a)]; and subsections (c) and (d) of such section 30 shall apply with respect to actions taken and exemptions granted under this subsection. Except as specifically provided in this subsection, the granting of an exemption to a project under this subsection shall in no case have the effect of waiving or limiting the application (to such project) of the second sentence of subsection (b) of this section.