Columbia State Bank, Appellant V. Normandy Park Investors, Respondent

Case Date: 01/17/2012
Court: Court of Appeals Division I
Docket No: 65959-6

 
DO NOT CITE. SEE GR 14.1(a).


Court of Appeals Division I
State of Washington

Opinion Information Sheet

Docket Number: 65959-6
Title of Case: Columbia State Bank, Appellant V. Normandy Park Investors, Respondent
File Date: 01/17/2012

SOURCE OF APPEAL
----------------
Appeal from King County Superior Court
Docket No: 09-2-06371-1
Judgment or order under review
Date filed: 08/20/2010
Judge signing: Honorable Gregory P Canova

JUDGES
------
Authored byC. Kenneth Grosse
Concurring:Ronald Cox
Anne Ellington

COUNSEL OF RECORD
-----------------

Counsel for Appellant(s)
 Donald Louis Anderson  
 Attorney at Law
 1201 Pacific Ave Ste 1200
 Tacoma, WA, 98402-4395

Counsel for Respondent(s)
 Andrew Alexander Guy  
 Stoel Rives
 600 University St Ste 3600
 Seattle, WA, 98101-3197

 Sandip Soli  
 Cairncross & Hempelmann PS
 524 2nd Ave Ste 500
 Seattle, WA, 98104-2323

 Charles Ennis Newton  
 Cairncross & Hempelmann PS
 524 2nd Ave Ste 500
 Seattle, WA, 98104-2323

 Michael Regeimbal  
 Regeimbal McDonald PLLC
 612 S 227th St
 Des Moines, WA, 98198-6826

 Scott E Feir  
 Montgomery Purdue Blankinship & Austin
 701 5th Ave Ste 5500
 Seattle, WA, 98104-7096
			

      IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

 COLUMBIA STATE BANK, a                      )
 Washington State banking corporation, )             No. 65959-6-I
                                             )
                       Appellant,            )       DIVISION ONE
                                             )
               v.                            )       UNPUBLISHED OPINION
                                             )
 NORMANDY PARK INVESTORS, LLC, )
 a Washington limited liability company; )
 and DIVERSIFIED PROPERTY                    )
 INVESTORS, LLC, a Washington                )
 limited liability company,                  )
                                             )
                       Defendants,           )
                                             )
 ANTINORI DEVELOPMENT, LLC, a                )
 Washington limited liability company,       )
                                             )
                       Respondent,           )
                                             )
SUPERIOR ASPHALT MAINTENANCE, )
INC., a Washington corporation; and          )
ELITE ELECTRICAL, INC., a                    )
Washington corporation,                      )       FILED: January 17, 2012
                                             )
                              Defendants.            )

        Grosse, J.  --  A party who provides labor and services to a property owner has a 

 statutory right to file a lien on that property to ensure payment for those services.     Here, 

 adjoining property owners agreed to have certain work performed on their property 

 pursuant to a reciprocal easement agreement.  The fact that the general contractor was 

 one of the co-owners of the property subject to the easement does not estop him from 

 attaching a lien to the other property for his fair share of the improvements made 

 thereto.   Accordingly, we affirm. 

No. 65959-6-I / 2

                                            FACTS

       On March 30, 2005, Normandy Park Towne Center, LLC (NPTC) and Normandy 

Park Investors, LLC (NPI) entered into a Reciprocal Easement Agreement (REA).   The 

REA established a perpetual, reciprocal non-exclusive easement for both parties'

benefit to establish a common driveway to provide ingress and egress to and from the 
parties' respective properties.  The REA was recorded on April 19, 2005.1          In August of 

the following year, Antinori Development, LLC (Antinori)  acquired the property from 

NPTC    and proceeded to construct the driveway between its property and NPI's 

property.  

       The REA set forth the procedure for sharing the cost of the common driveway:

       The party who is first to re-develop its property ("First Party") will develop a 
       conceptual design for the Common Driveway and deliver it to the other party 
       ("Second Party") for review and approval.  The parties will act reasonably in 
       developing a mutually agreeable design for the Common Driveway.  The parties 
       will equally share the cost of designing and constructing the Common Driveway, 
       including unanticipated costs and cost overruns.  The parties intend to equally 
       bear the risks of constructing the Common Driveway.

       The First Party shall construct the common driveway during the re-development 
       work.  The First Party will, from time to time, request reimbursement from the 
       other party ("Second Party") for half the cost of completed work on the common 
       driveway.  The Second Party will pay the First Party within 20 days of receiving a 
       request for reimbursement.  The Second Party may request reasonable 
       documentation of costs incurred, completion of work, and release of liens by 
       contractors and subcontractors.

Antinori and NPI agreed that the construction of the common driveway would include

construction of an onsite storm drain, a shared water main, a storm water vault, 

roadway paving, as well as electrical, telephone, and television utilities.  Antinori hired 

Pivetta Brothers Construction (Pivetta).  Pivetta began excavation and storm water 

1 King County Recording No. 20050419001552.

                                               2 

No. 65959-6-I / 3

work on October 11, 2006.  Throughout the project, Antinori sought and received 

approval from NPI and its agents for the work undertaken and the costs of construction 

providing NPI with work orders, invoices and documentation, and costs associated with 

the construction.  The driveway was completed without                NPI having made any 

payments.  NPI's share of the cost for construction amounted to $164,923.44.  The final 

punch list was completed on January 5, 2009.  When NPI failed to pay, Antinori 
recorded its lien claim with King County on January 16, 2009.2

       On February 3, 2009, Antinori filed a complaint naming NPI as the owner.              On 

that same day, Columbia State Bank (Columbia) filed a lawsuit against NPI alleging 

various causes of action arising from NPI's and Diversified Property Investors, LLC's 

(DPI) defaults on its loan to NPI for construction of a shopping mall.        On December 4, 

2009,  Columbia  amended its complaint and added Antinori as a defendant.  On 

February 19, 2010, Antinori's suit was consolidated with Columbia's foreclosure action.  

       On July 9, 2010, the trial court granted partial summary judgment to Antinori, 

finding that NPI was liable and that Antinori's lien had priority over Columbia's lien.  On 

August 20, 2010, after a bench trial, the trial court entered a judgment and decree of 

foreclosure for Columbia as to its claims against NPI and DPI.  Columbia appeals.

                                          ANALYSIS

       Columbia argues that the trial court erred in finding that Antinori's lien was valid 

and had priority over its lien.  Columbia first argues that Antinori was not entitled to a 

lien because the REA did not create a specific right to do so.  However,  RCW 

60.04.021 specifies who may claim a lien:

2 King County Recording No. 200901160000388.

                                               3 

No. 65959-6-I / 4

       Except as provided in RCW 60.04.031, any person furnishing labor, professional 
       services, materials, or equipment for the improvement of real property shall have 
       a lien upon the improvement for the contract             price of labor, professional 
       services, materials, or equipment furnished at the instance of the owner, or the 
       agent or construction agent of the owner.

       As noted in the REA, the common driveway is situated on both properties.  

Pursuant to both the REA and agreements between Antinori and NPI, Antinori, acting 

as the general contractor, made improvements to both the Antinori property and the 

NPI property via its construction of the common driveway and associated utilities.          The 

fact that the work was performed as the result of the REA does not remove Antinori's 

right to pursue a mechanics' lien.  "A lien is an encumbrance on property to secure 
payment of a debt."3    RCW 60.04.141 requires that a mechanics' lien be filed within 90 

days of the work performed on or materials furnished to the subjected property.  Here, 

Antinori recorded its lien on January 16, 2009, eleven days after the subcontractor, 

Superior Asphalt Maintenance, Inc., completed construction. Thus, the lien was timely.  

       Antinori's lien was first in line because excavation and mobilization of equipment 

for the construction began on October 11, 2006.  Columbia recorded its deed of trust 
on November 1, 2006.4 RCW 60.04.061 provides:

       The claim of lien created by this chapter upon any lot or parcel of land shall be 
       prior to any lien, mortgage, deed of trust, or other encumbrance which attached 
       to the land after or was unrecorded at the time of commencement of labor or 
       professional services or first delivery of materials or equipment by the lien 
       claimant.[5]

Pursuant to this statute, mechanics' liens "relate back to the commencement of the 

3 S.D. Deacon Corp. of Wash. v. Gaston Bros. Excavating, 150 Wn. App. 87, 89 206 
P.3d 689 (2009).
4 King County Recording No. 20061101001227.
5 (Emphasis added.)

                                               4 

No. 65959-6-I / 5

services."6   The statute explicitly provides that "[t]he claim of lien created by this 

chapter," that is, the lien created when a property owner requisitions materials or 

services, "shall be prior" to other later-attached or later-recorded encumbrances.  In 

other words, a debt that is subject to the lien relates back to the date work first 

commenced, here, October 11, 2006, almost a month prior to Columbia filing its lien.  

Thus, Antinori's lien is first in priority.

       Columbia next claims that the work performed by Pivetta was outside the scope 

of the REA and therefore not properly subject to the lien.  Columbia argues that the 

REA provided that the parties pay the costs of "constructing, installing, maintaining, 

repairing, altering and replacing the paving, roadways, driving lanes, striping and other 

surface improvements." That language, Columbia contends, did not include the work 

performed by Pivetta, to wit:  excavation and construction of onsite storm drain, shared 

water main, and storm water vault.  But declarations submitted by Antinori showed that 

the parties agreed to do this additional work as part of the construction under the REA.  

Columbia does not dispute that the parties so agreed.    

       Columbia then argues that if the work is subject to a lien, the lien here was 

untimely and cannot relate back because the work done in October by Pivetta was in 

reality done under a separate and distinct contract.  To support this theory, Columbia 
relies on Anderson v. Taylor.7  In Anderson, a subcontractor entered into a contract 

with the general contractor who was paid by the homeowner.  The subcontractor 

stopped worked and the general contractor went out of business.  The subcontractor 

6 Zervas Group Architects, PS v. Bay View Tower, LLC, 161 Wn. App. 322, 254 P.3d 
895 (2011).
7 55 Wn.2d 215, 347 P.2d 576 (1959).

                                               5 

No. 65959-6-I / 6

then contracted with the homeowner to complete the tile work on the residence.  The 

subcontractor then filed a lien on the residence that included amounts owed him by the 

general contractor for the previous work.  The court found that the subcontractor 

provided labor on a new contract separate and distinct from the contract with the 

general contractor. Unlike in Anderson, where there was a separate, distinct and 

severable contract with different parties, the contract here was performed under one 

contract with and for the same parties.       The parties' oral agreements enhanced the 

REA, they were not separate and distinct therefrom.

       Finally, Columbia argues that the lien is invalid because it fails to comply with 

the "strict requirements of the lien foreclosure statute" by failing to name NPI as both 

the person indebted to Antinori and the owner of the liened property. The statute 

provides that the notice of claim "[s]hall state in substance and effect" the "name of the 
person indebted to the claimant."8        In support of its position of strict construction, 

Columbia cites this court's decision in Williams v. Athletic Field, Inc.9        But that case 

was overruled by the Supreme Court,10 which held that the mechanics' lien statute's 

mandate of liberal construction has not been supplanted by a common law rule of strict 
construction.11  Here, as in Williams, there is no dispute that the claimants provided 

services subject to a lien and claimed a lien against the appropriate property.  Rather,

the dispute is about whether the form of the lien is proper.  Because NPI is both the 

owner and the indebted party, and is named by Antinori, Antinori has substantially 

8 RCW 60.04.091.
9 155 Wn. App. 435, 228 P.3d 1297 (2010).
10 Williams v. Athletic Field, 172 Wn.2d 683, 261 P.3d 109 (2011).
11 Williams, 172 Wn.2d at 697.

                                               6 

No. 65959-6-I / 7

complied with the requirements of the statute.  As our Supreme Court stated, "To the 

extent  Lumberman's or other cases suggest that the statute's mandate of liberal 

construction has been supplanted by a common law rule of strict construction, we 
disapprove them."12    Moreover, Washington courts have repeatedly stated that in order 

to establish a valid claim of lien, a claimant need only substantially comply with the 
requirements of RCW 60.04.091.13

        Columbia also seems to argue that even though the lien statute provides that a 

claimant need only serve the owner of the property and not mortgagees, such as the 

bank, it is "nonsensical" and thus should not be permitted to foreclose upon the 
property without any notice to a mortgagee.14      Columbia cites no valid authority for this 

proposition.  The statute does not require the mortgagee to be served, it provides for 

service on the owner.  We presume the legislature meant exactly what it said.  Plain 

words do not require further construction.

Attorney Fees  

       The trial court correctly awarded Antinori its attorney fees and costs as provided 

under RCW 60.04.181.  Since Antinori also prevails on appeal, it is entitled to fees and 

costs.

WE CONCUR: