|
DO NOT CITE. SEE GR 14.1(a).
Court of Appeals Division I
State of Washington
Opinion Information Sheet
| Docket Number: |
66267-8 |
| Title of Case: |
Pacific Northwest Earthworks, Llc., Appellant V. The City Of Bellevue, Washington, Respondent |
| File Date: |
02/21/2012 |
SOURCE OF APPEAL
----------------
| Appeal from King County Superior Court |
| Docket No: | 10-2-16185-6 |
| Judgment or order under review |
| Date filed: | 10/22/2010 |
| Judge signing: | Honorable Catherine D Shaffer |
JUDGES
------
| Authored by | Anne Ellington |
| Concurring: | J. Robert Leach |
| Stephen J. Dwyer |
COUNSEL OF RECORD
-----------------
Counsel for Appellant(s) |
| | Bruce Paul Babbitt |
| | Attorney at Law |
| | 999 3rd Ave Ste 1900 |
| | Seattle, WA, 98104-4028 |
Counsel for Respondent(s) |
| | Cheryl Ann Zakrzewski |
| | City of Bellevue |
| | 450 110th Ave Ne |
| | Po Box 90012 |
| | Bellevue, WA, 98009-9012 |
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
DIVISION ONE
PACIFIC NORTHWEST EARTHWORKS LLC, ) No. 66267-8-I
a Washington limited liability company, ) consolidated with
) No. 66362-3-I
Appellant, )
)
v. )
)
THE CITY OF BELLEVUE, WASHINGTON, ) UNPUBLISHED OPINION
a municipal corporation, )
) FILED: February 21, 2012
Respondent. )
)
Ellington, J. -- Pacific Northwest Earthworks LLC (Earthworks) was the low
bidder on a public works contract to install sewer lines for the city of Bellevue (City).
Earthworks claims it is entitled to compensation beyond the contract price because the
City misrepresented the undertaking. We disagree, and affirm the trial court's
dismissal and its award of attorney fees and costs to the City.
BACKGROUND
The City sought bids on a project to excavate for and install sanitary sewer lines
and manholes along some 500 linear feet in the Cougar Mountain area. Prospective
bidders received a construction contract packet that included bid instructions, special
contract information, the general conditions and technical specifications applicable to
No. 66267-8-I/2
the project, detailed drawings, and a geotechnical report from GeoEngineers. One
stated purpose of the GeoEngineers report was to "provide conclusions and
recommendations for . . . [e]arthwork and site preparation including . . . trench
excavation considerations."1
To prepare its report, GeoEngineers explored the subsurface conditions of the
project site by drilling two borings along the route. It reported the bedrock material was
sandstone and siltstone consistent with "Blakeley Formation bedrock," which is
"generally friable (crumbles easily by rubbing with fingers) . . . and is very soft with
respect to rock hardness."2 It also noted the bedrock did not meet the criteria for "rock
excavation" under the Washington State Department of Transportation (WSDOT)
standard specifications:
Rock excavation shall cover the removal and disposal of rock that
requires systematic drilling and blasting for its removal, and also boulders
exceeding ½-cubic yard. Ledge rock, boulders, or stones shall be
removed to provide a minimum clearance of 4-inches under the pipe.
Hardpan, hard clay, glacial till, sandstone, siltstone, shale, or other
sedimentary rocks, which are soft, weathered, or extensively fissured will
not be classified as rock excavation. Rock is defined as one that has . . .
unconfined compressive strength at field moisture content of more than
2,000-PSI.[3]
GeoEngineers opined that the trench excavation could be accomplished "with
conventional excavation equipment, such as trackhoes or dozers."4
1 Clerk's Papers at 284.
2 Clerk's Papers at 286.
3 Wash. St. Dep't of Transp. Standard Specifications for Road, Bridge, and
Municipal Construction, section 7-09.3(7)B (2008) (emphasis added).
4 Clerk's Papers at 287.
2
No. 66267-8-I/3
GeoEngineers also explained, however, that "geoscience practices . . . are far
less exact than other engineering and natural science disciplines . . . [which] could lead
to disappointments, claims, and disputes."5 Its report therefore included a section
entitled "Report Limitations and Guidelines for Use," which made several disclaimers:
? The geotechnical report was prepared for exclusive use of the City
and not intended for use by others unless agreed to in writing;
? The report was compiled for a civil engineer or architect and may not
fulfill the needs of a construction contractor;
? Interpretation of subsurface conditions was based on field
observations only from the widely spaced sampling locations at the
site;
? Actual subsurface conditions may differ, sometimes significantly, from
those indicated in the report;
? The report, conclusions and interpretations should not be construed
as a warranty of subsurface conditions;
? Contractors could misinterpret the report and could avoid risk by
participating in pre-bid and pre-construction conferences;
? When providing the report to contractors, the City should provide the
complete report and include with it a letter advising them that it was
not prepared for bid development; and
? The City should be sure contractors have sufficient time to perform
additional study.6
The City also disclaimed liability for reliance upon its representations:
[T]he bidder shall examine the site of the work and ascertain for himself
all the physical conditions in relation thereto. . . . He will not be entitled to
additional compensation if he subsequently finds the conditions to require
other methods or equipment that he did not anticipate. . . .
Any statement or representation made by an officer, agent, or
5 Clerk's Papers at 307.
6 See Clerk's Papers at 305-07.
3
No. 66267-8-I/4
employee of the [City] with respect to the physical conditions appertaining
to the site of the work shall not be binding upon the [City].[7]
The construction contract included a bid item list for bidders to enter the price for
various components of the project. Bid item 3 was for rock excavation. The contract
provided that additional payment for rock excavation would require demonstration that
the material excavated met the WSDOT definition of "rock." The City further explained:
Payment for rock excavation when authorized by the [City]
Engineer shall be made at the Contract Price bid per cubic yard. The
Contract Price shall include full compensation for furnishing all labor,
materials, tools, equipment, and incidentals, and for completing all work
involved . . . .
. . . .
Excavated material meeting the [WSDOT] Standard Specifications
definition of rock is not expected. . . . This contingent bid item is included
for use only if such rock excavation is encountered. [8 ]
Before bidding on the project, Earthworks investigated the site three times to
ascertain traffic conditions, power line locations, and access difficulties. It did not make
an independent subsurface investigation because the site was a traveled, paved road.
Fifteen contractors bid on the project. The amounts bid for rock excavation
varied widely, from $0.50 to $250.00 per cubic yard. Earthworks submitted the lowest
total bid of $158,804, with $2.50 per cubic yard for rock excavation.
Earthworks started the project using a 45,000 pound Komatsu 200 excavator
with "tiger teeth," which it owned. When it encountered rock that was too hard for the
Komatsu, Earthworks rented a 60,000 pound Kobelco 215 excavator for two weeks. It
7 Clerk's Papers at 108-09.
8 Clerk's Papers at 202.
4
No. 66267-8-I/5
is undisputed that the Komatsu and Kobelco are "conventional excavation equipment."
Earthworks hired an outside company to perform testing on some of the
excavated material, which reported the mean compressive strengths of two sets of
samples as 2,200 and 2,315 psi, respectively. Earthworks claimed it excavated 284
cubic yards of rock as defined by WDOT.
Claiming the presence of rock was unanticipated and constituted a "changed
condition" on the job site, Earthworks sought compensation outside the terms of the
contract. It requested $55,456 to cover the costs of equipment rental and extra labor.9
The City denied the request.
Earthworks sued the City for breach of contract, alleging the City "fail[ed] to
make an equitable adjustment to the contract to compensate the contractor for its
misrepresentation of [the] site condition."10 The City moved for summary judgment,
arguing there was no evidence of misrepresentation and that, as a matter of law, there
were no changed conditions entitling Earthworks to compensation outside the terms of
the contract. The trial court agreed and dismissed the case. It awarded the City
attorney fees and costs as the prevailing party.
Earthworks appeals.
DISCUSSION
The usual standard of review for summary judgment applies.11 Determinations of
9 The average hourly rate for labor was about $40 per hour. The total cost of the
rental equipment was $3,100.
10 Clerk's Papers at 4.
11 This court reviews summary judgment orders de novo, engaging in the same
inquiry as the trial court and viewing all facts and reasonable inferences therefrom in
5
No. 66267-8-I/6
"reasonableness" are generally questions of fact, but may be disposed of on summary
judgment if, construing the evidence in favor of the nonmoving party, a reasonable
person could reach only one conclusion.12
Compensation for Rock Excavation
Where plans or specifications for an excavation contract lead a contractor
reasonably to believe that certain conditions exist and may be relied upon in making a
bid, the contractor will be entitled to compensation for extra work or expense made
necessary by the unanticipated condition.13 Reliance is reasonable if the contractor
has made a reasonable investigation under the circumstances.14 Where no such
representation exists, or reliance was not reasonable, a contractor who agrees to do a
job for a fixed sum will not be entitled to additional compensation because of
unforeseen difficulties.15
Earthworks points out that the City's geotechnical report showed borings
the light most favorable to the nonmoving party. Halleran v. Nu West, Inc., 123 Wn.
App. 701, 709-10, 98 P.3d 52 (2004). The moving party bears the burden of
demonstrating the absence of any genuine issue of fact and entitlement to judgment as
a matter of law; thereafter, the nonmoving party must set forth specific facts evidencing
a genuine issue of material fact. Magula v. Benton Franklin Title Co., Inc., 131 Wn.2d
171, 182, 930 P.2d 307 (1997).
12 See generally Basin Paving Co. v. Mike M. Johnson, Inc., 107 Wn. App. 61,
65-68, 27 P.3d 609 (2001).
13 Dravo Corp. v. Mun. of Metro. Seattle, 79 Wn.2d 214, 218, 484 P.2d 399
(1971) (quoting Maryland Cas. Co. v. Seattle, 9 Wn.2d 666, 670, 116 P.2d 280 (1941)).
14 Clevco, Inc. v. Mun. of Metro.Seattle, 59 Wn. App. 536, 542-43, 799 P.2d
1183 (1990); Nelson Constr. Co. of Ferndale, Inc. v. Port of Bremerton, 20 Wn. App.
321, 328-29, 582 P.2d 511 (1978).
15 Dravo, 79 Wn.2d at 218 (quoting Maryland Cas. Co., 9 Wn.2d at 670); see
also Basin Paving, 107 Wn. App. at 65-66; Clevco, 59 Wn. App. at 542-43; Nelson, 20
Wn. App. at 328-29.
6
No. 66267-8-I/7
containing only soft rock, and that the City did not expect the contractor to encounter
subsurface rock meeting the WSDOT standards.
But this does not amount to a lack of anticipation. Both the City and
GeoEngineers warned bidders against reliance on the geotechnical report, and the City
specifically disclaimed liability for expenses from subsurface conditions unanticipated
by the contractor. The geotechnical report warned contractors not to draw conclusions
about subsurface conditions based on GeoEngineers' analysis of the two widely-
spaced borings. Most notably, the contract included a contingent bid item for rock
excavation. The City clearly foresaw the possibility that harder rock might be present at
the project site, and Earthworks submitted its bid price for exactly that.
Earthworks points to the fact that some other bidders' excavation prices were
even lower that the Earthworks price, and concludes these other contractors similarly
relied upon the City's bid information and expected to encounter no rock, so
Earthworks' expectation was reasonable. But most of the bidders' prices were higher
than the Earthworks bid, so this inference is not supported, and in any event, there is
no evidence showing why other contractors bid as they did.
7
No. 66267-8-I/8
The rule for excavation contracts is that recovery of additional compensation for
unforeseen conditions is limited to situations where the "condition complained of could
not reasonably have been anticipated by either party."16 The rule has been applied in a
long line of cases involving public works contracts for excavation or dredging, including
Basin Paving Company v. Mike M. Johnson,17 Dravo Corporation v. Municipality of
Metropolitan Seattle,18 Maryland Casualty v. City of Seattle,19 and Nelson Construction
Company of Ferndale, Inc. v. Port of Bremerton.20 The government in these cases
either disclaimed liability for information it provided about subsurface conditions or
gave no information about subsurface conditions at all.21 The contractors failed to
include in the contract price the cost of dealing with certain subsurface conditions.22 All
16 Basin Paving, 107 Wn. App. at 65 (citing cases).
17 107 Wn. App. 61 (court refused to grant contractor extra-contractual
compensation for unanticipated subsurface conditions where city disclaimed liability for
accuracy of boring tests and for any conclusions drawn therefrom, and where it advised
the contractor it would not pay additional compensation for rock excavation).
18 79 Wn.2d. 214 (court refused to grant contractor extra-contractual
compensation for unanticipated subsurface conditions where city disclaimed accuracy
of subsurface test results and contractor assumed risk by terms of contract).
19 9 Wn.2d 666 (court refused to grant contractor extra-contractual compensation
for unanticipated subsurface conditions where city provided no warranty regarding
those conditions).
20 20 Wn. App. 321 (court refused to grant contractor extra-contractual
compensation for unanticipated subsurface conditions it encountered where those
conditions were foreseeable based on the specifications and contractor failed to follow
contractual procedure for additional compensation).
21 See Dravo, 79 Wn.2d. at 215-16, 218; Maryland Cas., 9 Wn.2d at 668, 675-
76; Basin Paving, 107 Wn. App. at 63-64; Nelson, 20 Wn. App. at 323-25.
22 See Dravo, 79 Wn.2d. at 216-17; Maryland Cas., 9 Wn.2d at 677; Basin
Paving, 107 Wn. App. at 64-67; Nelson, 20 Wn. App. at 325-26.
8
No. 66267-8-I/9
risk of unanticipated subsurface conditions was allocated to the contractors.23
Earthworks contends that in those cases "there could be no dispute but that the
basic information and test borings provided to the contractors for bidding purposes
were accurate."24 But nothing in the record indicates the analysis of GeoEngineers' two
boring samples was not accurate. Further, the City and GeoEngineers actually
disclaimed reliance upon the accuracy of the geotechnical report and pointed out that
the information came from only two samples.
The possibility that Earthworks would encounter rock was foreseeable, and
Earthworks is not entitled to additional compensation. We affirm the court's order on
summary judgment and its award of attorney fees and costs to the City as the prevailing
party pursuant to the contract.
WE CONCUR:
23 See Dravo, 79 Wn.2d. at 218-19, 222; Maryland Cas., 9 Wn.2d at 670, 680;
Basin Paving, 107 Wn. App. at 67-68; Nelson, 20 Wn. App. at 329.
24 Appellant's Br. at 16.
9
|